Public Meeting Notices: Add a Public Noticehttp://fdotsp.dot.state.fl.us/sites/publicnotices/Lists/add a public meeting/AllItems.aspxRSS feed for the Add a Public Notice list.enSunset Strip Complete Streets Project Ribbon Cutting & Bike Ridehttp://fdotsp.dot.state.fl.us/sites/publicnotices/Lists/add a public meeting/DispForm.aspx?ID=5333
  • Removing old asphalt and resurfacing the roadway
  • Upgrading crosswalk ramps to meet ADA requirements
  • Adding roadway lighting 
  • Upgrading existing drainage structures and adding one new drainage structure east of NW 68 Avenue 
  • Replacing the signalized intersection at NW 64 Avenue with a roundabout 
  • Replacing the four-way stop sign at NW 19 Street with a roundabout 
  • Reconstructing sidewalks in various locations 
  • Upgrading signs and pavement markings 
  • Adding bike lanes throughout the corridor:
  • Construction on this $3.8 million project began in June 2017. All work on this project is expected to be complete in early August.   Public participation is solicited without regard to race. color, national origin, age, sex, religion, disability or family status.  ]]>
    Kelleher, BarbaraTue, 17 Jul 2018 17:41:05 GMThttp://fdotsp.dot.state.fl.us/sites/publicnotices/Lists/add a public meeting/DispForm.aspx?ID=5333
    Design Public Mtg: New England Blvd & Sandalfoot Blvd Bridges http://fdotsp.dot.state.fl.us/sites/publicnotices/Lists/add a public meeting/DispForm.aspx?ID=5266
  • The new bridge will have two 12-foot travel lanes in each direction, 5-foot shoulders/bike lanes on both sides and 6.5-foot sidewalks on both sides
  • Reconstruction of the roadway at the bridge approaches
  •  Proposed Sandalfoot Boulevard Bridge Improvements:
    • The new bridge will have four 11-foot travel lanes in each direction, a 10-foot median turn lane, 5-foot shoulder/bike lanes on both sides and 6.5-foot sidewalks on both sides 
    • Upgraded guardrails
    • Reconstruction of the roadway and sidewalk at the bridge approaches on both sides
    Construction of this project is expected to begin in September 2019 with anticipated completion in September 2020. The estimated cost for the New England Bridge is $1.38 million. The estimated cost for the Sandalfoot Bridge is $1.79 million. Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status . Persons who require special accommodations under the Americans with Disabilities Act (ADA) or persons who require translation services (free of charge) should contact Maria Formoso, PE, FDOT Project Manager at least seven days prior to the meeting. She can be reached by phone at 954-777-4677 or toll free at 1-866-336-8435 ext. 4677 or by email at maria.formoso@dot.state.fl.us.  ]]>
    Kelleher, BarbaraMon, 21 May 2018 20:14:35 GMThttp://fdotsp.dot.state.fl.us/sites/publicnotices/Lists/add a public meeting/DispForm.aspx?ID=5266
    SW 56th Ave, SW 62nd Ave and North 64th Ave Public Meetinghttp://fdotsp.dot.state.fl.us/sites/publicnotices/Lists/add a public meeting/DispForm.aspx?ID=5311Le, Thuc H.Wed, 27 Jun 2018 19:54:06 GMThttp://fdotsp.dot.state.fl.us/sites/publicnotices/Lists/add a public meeting/DispForm.aspx?ID=5311Design Public Workshop: Broward Mobility Projects http://fdotsp.dot.state.fl.us/sites/publicnotices/Lists/add a public meeting/DispForm.aspx?ID=5335
  • Widening SW 56th Avenue from Pembroke Road to Stirling Road to provide 7-foot-wide buffered bicycle lanes and Adding sidewalk, where needed
  • Restriping SW 62nd Avenue from County Line/SW 41st Street to add shared lane pavement markings and Adding sidewalk , as needed, to fill gaps
  • Restriping North 64th Avenue from Hollywood Boulevard to Sheridan Street to add shared lane pavement markings
  •  Construction of these improvements is scheduled to begin in Summer 2019 with anticipated completion in Fall 2020. The estimated construction cost of these improvements is $8.5 million.  Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status.  Persons who require special accommodations under the Americans with Disabilities Act or persons who require translation services (free of charge) should contact Thus Le, FDOT Project Manager, at least seven days prior to the workshop.  He can be reached by phone at 954-777-4552 , by email at Thuc.Le@dot.state.fl.us or by US Mail at FDOT District Four, 3400 West Commercial Boulevard, Fort Lauderdale FL 33309.  ]]>
    Kelleher, BarbaraTue, 17 Jul 2018 19:56:05 GMThttp://fdotsp.dot.state.fl.us/sites/publicnotices/Lists/add a public meeting/DispForm.aspx?ID=5335
    Construction Open House: Peters Rd from Pine Island Rd to University Drhttp://fdotsp.dot.state.fl.us/sites/publicnotices/Lists/add a public meeting/DispForm.aspx?ID=5334
  • Widening, resurfacing and restriping the roadway to accommodate 5-foot-wide designated bike lanes with a 3-foot-wide buffer and two 11-foot-wide travel lanes in each direction
  • Installing curb and gutter along the median and outside lanes at the approaches to intersections and at bus stops
  • Modifying pedestrian curb ramps to meet Americans with Disabilities (ADA) requirements
  • Relocating drainage structures
  • Upgrading roadway lighting at University Drive
  •  Construction is expected to begin the week of August 19 with anticipated completion in Spring 2019. The construction cost of these improvements is $1.4 million. During construction access to properties will be maintained at all times. Two 10-foot travel lanes will be maintained in each direction for the majority of the project. Lane closures will be allowed between 10 a.m. and 3 p.m. or overnight between 8 p.m. and 7:30 a.m. , as needed. Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. Persons who require special accommodations under the Americans with Disabilities Act (ADA) or persons who require translation services (free of charge) should contact one of these project staff at least seven days prior to the Open House:   Matthew May, FDOT Construction Project AdministratorPhone: 954-940-7519Email: Matthew.May@dot.state.fl.us Mrs. Dayana. Diaz, Community Outreach SpecialistPhone: 954-940-7585Email: ddiaz@corradino.com  ]]>
    Kelleher, BarbaraTue, 17 Jul 2018 18:08:30 GMThttp://fdotsp.dot.state.fl.us/sites/publicnotices/Lists/add a public meeting/DispForm.aspx?ID=5334
    Public Hearing: SR 804/Boynton Beach Blvd from Jog Rd to Congress Avenuehttp://fdotsp.dot.state.fl.us/sites/publicnotices/Lists/add a public meeting/DispForm.aspx?ID=5328
  • Removing old asphalt and resurfacing the existing pavement
  • Widening to accommodate a 4-foot-wide bike lane in each direction
  • Installing a directional median opening at Pear Tree Circle
  • Upgrading sidewalks along the corridor with Americans With Disabilities Act compliant curb ramps
  • Upgrading traffic signals and lighting at seven intersections
  •  Construction is anticipated to begin in Fall 2019 with completion in Fall 2021. the estimated construction cost of these improvements is $8.1 million.  Public participations is solicited without regard to race, color, national origin, age, sex, religion, disability or family status.  Persons who require accommodations under the Americans with Disabilities Act (ADA) or person who require translation services (free of charge) should contact July Jimenez, PE, FDOT's Project Manager, at least seven days prior to the Public Hearing. She can be reached by phone, toll free at 1-866-336-8435 ext. 4415, by email at July.Jimenez@dot.state.fl.us or by US Mail at FDOT District Four, 3400 West Commercial Boulevard, Fort Lauderdale FL 33309. Persons wishing to submit written statements or other exhibits, in place of or in addition to oral statements, may do so at the hearing or by sending them to July Jiminez, FDOT's Project Manager to the email or US Mail address above. All exhibits or statements postmarked on or before August 29, 2018 will become part of the Public Hearing record.   ]]>
    Kelleher, BarbaraMon, 16 Jul 2018 20:51:32 GMThttp://fdotsp.dot.state.fl.us/sites/publicnotices/Lists/add a public meeting/DispForm.aspx?ID=5328